Project design matrix (PDM) worksheet
Enter the logical chain of overall goal → project purpose → outputs → activities vertically, and the corresponding indicators, means of verification and external conditions horizontally. Complete the problem and objective trees first.
Project design matrix (PDM) worksheet
Basic information
Enter an overview of the project
Completed example for this section (fictional)
This fictional example is for explanation. Adapt it to your own program. Your entries will not change.
- Project name
- Community counseling accompaniment program (fictional)
- Target area and participants
- Area A; 20 residents seeking counseling
- Implementation period
- April 2026–March 2027
- Date prepared and prepared by
- April 1, 2026 / counseling officer
Reason for this entry: The numbers and period define the scope of this fictional plan.
Writing tips and explanation for this section
About this section
Enter an overview of the project
The numbers and period define the scope of this fictional plan.
View the method explanationWriting tips
Follow each field’s heading to record the program name, focus, period, and other details. Leave undecided matters clearly marked as unresolved.
Read the full fictional exampleMain PDM matrix
Complete each row and column (multiple activity rows are allowed)
Completed example for this section (fictional)
This fictional example is for explanation. Adapt it to your own program. Your entries will not change.
Scroll horizontally to view the table
| Hierarchy of objectives | Indicators (OVI) | Means of verification for indicators | External conditions (assumptions) |
|---|---|---|---|
| Overall goal: improved access to needed support | Proportion of people able to use support for their difficulties | Follow-up records based on consent | The relevant scheme continues |
| Project purpose: residents who wish to apply proceed with applications | Number of the 20 interested residents who proceed with applications | Counseling and application status records | A service meeting scheme requirements is available |
| Output: counseling and accompaniment provided | 20 first-time counseling users; accompaniment sessions for those requesting them | Implementation records with duplicates removed | The individual wishes to participate |
| Activities: counselor training and accompaniment coordination | 2 training sessions and staff assignments | Training records and rosters | Counselors are available to participate |
Reason for this entry: Use different verification sources for different objective levels.
Scroll horizontally to view the table
| Hierarchy of objectives | Indicators (OVI) | Means of verification for indicators | External conditions (assumptions) |
|---|---|---|---|
Writing tips and explanation for this section
About this section
Complete each row and column (multiple activity rows are allowed)
Use different verification sources for different objective levels.
View the method explanationWriting tips
Keep the information in each row aligned. Scroll wide tables horizontally to see every column.
Read the full fictional exampleAssumption notes (additional details on major risks)
Describe high-risk external conditions and responses
Completed example for this section (fictional)
This fictional example is for explanation. Adapt it to your own program. Your entries will not change.
Scroll horizontally to view the table
| External conditions | Likelihood (high / medium / low) | Risk responses |
|---|---|---|
| The service has sufficient intake capacity | Medium (team hypothesis) | Check booking availability before starting and identify alternative services |
Reason for this entry: Do not present estimated risk levels as observed values; determine what actions will verify them.
Scroll horizontally to view the table
| External conditions | Likelihood (high / medium / low) | Risk responses |
|---|---|---|
Writing tips and explanation for this section
About this section
Describe high-risk external conditions and responses
Do not present estimated risk levels as observed values; determine what actions will verify them.
View the method explanationWriting tips
Keep the information in each row aligned. Scroll wide tables horizontally to see every column.
Read the full fictional exampleVertical logic check
Completed example for this section (fictional)
This fictional example is for explanation. Adapt it to your own program. Your entries will not change.
- ☑ Checked: If activities are implemented (and external conditions hold), outputs will be achieved
- ☑ Checked: If outputs are achieved (and external conditions hold), the project purpose will be achieved
- ☑ Checked: If the project purpose is achieved (and external conditions hold), it will contribute to the overall goal
- ☐ Not checked: Each indicator meets SMART criteria
- ☑ Checked: Means of verification are recorded for every indicator
Reason for this entry: Some indicator deadlines and target levels remain undecided. Agree on them with stakeholders before use.
Writing tips and explanation for this section
About this section
Some indicator deadlines and target levels remain undecided. Agree on them with stakeholders before use.
View the method explanationWriting tips
Read each item and check those you have confirmed. Do not use the fictional example’s checkbox states as findings about your own program.
Read the full fictional exampleBefore writing, check when to use the worksheet and what completion involves
Project design matrix (PDM) worksheet is a worksheet for applying Logical Framework (Logframe / LFA) in meetings or individual work. For the overall duration of the method, use “Illustrative estimate (adjust for scale and staffing): 1–3 days (PDM development workshop)” as a reference, adjusting for scale and resources. Fill in what you know provisionally and leave unresolved matters as questions to check next.
When this worksheet is useful
- Throughout planning, consensus building, monitoring and evaluation of ODA and international development projects
- When a recipient organization requires a logframe or PDM. Check its specific format and definitions before use.
- Agreeing on a shared hierarchy of objectives in projects involving multiple donors or implementing agencies
Participants and preparation
Program officers, evaluation officers and key stakeholders. Include people who can verify the plan’s assumptions.
Bring the materials used for decisions, existing data, and differing stakeholder views to help complete the worksheet.
Suggested order
- 1. Basic informationEnter an overview of the project
- 2. Main PDM matrixComplete each row and column (multiple activity rows are allowed)
- 3. Assumption notes (additional details on major risks)Describe high-risk external conditions and responses
- 4. Vertical logic check
Signs the worksheet is ready for review
- Project design matrix (PDM)
- Problem and objective trees
- Plan of operations (PO)
Cautions for review
- Confusing the project purpose with the overall goal: the purpose is the situation the project should achieve; the overall goal is the broader objective beyond it
- Using only counts of activities as indicators, without measuring changes for participants (outcomes)
- Avoiding real risks by listing external conditions that are too obvious, such as “no war,” or too optimistic, such as “strong government commitment”
Read a completed fictional example (your entries will not change)
The following fictional example illustrates the design of a 1-year community project combining counselor training and counseling accompaniment.
Basic information
- Project name
- Community counseling accompaniment program (fictional)
- Target area and participants
- Area A; 20 residents seeking counseling
- Implementation period
- April 2026–March 2027
- Date prepared and prepared by
- April 1, 2026 / counseling officer
Reason for this entry: The numbers and period define the scope of this fictional plan.
Main PDM matrix
Scroll horizontally to view the table
| Hierarchy of objectives | Indicators (OVI) | Means of verification for indicators | External conditions (assumptions) |
|---|---|---|---|
| Overall goal: improved access to needed support | Proportion of people able to use support for their difficulties | Follow-up records based on consent | The relevant scheme continues |
| Project purpose: residents who wish to apply proceed with applications | Number of the 20 interested residents who proceed with applications | Counseling and application status records | A service meeting scheme requirements is available |
| Output: counseling and accompaniment provided | 20 first-time counseling users; accompaniment sessions for those requesting them | Implementation records with duplicates removed | The individual wishes to participate |
| Activities: counselor training and accompaniment coordination | 2 training sessions and staff assignments | Training records and rosters | Counselors are available to participate |
Reason for this entry: Use different verification sources for different objective levels.
Assumption notes (additional details on major risks)
Scroll horizontally to view the table
| External conditions | Likelihood (high / medium / low) | Risk responses |
|---|---|---|
| The service has sufficient intake capacity | Medium (team hypothesis) | Check booking availability before starting and identify alternative services |
Reason for this entry: Do not present estimated risk levels as observed values; determine what actions will verify them.
Vertical logic check
- ☑ Checked: If activities are implemented (and external conditions hold), outputs will be achieved
- ☑ Checked: If outputs are achieved (and external conditions hold), the project purpose will be achieved
- ☑ Checked: If the project purpose is achieved (and external conditions hold), it will contribute to the overall goal
- ☐ Not checked: Each indicator meets SMART criteria
- ☑ Checked: Means of verification are recorded for every indicator
Reason for this entry: Some indicator deadlines and target levels remain undecided. Agree on them with stakeholders before use.
Common errors in judgment
Writing “staff make an effort” as an external condition
How to revise: Place staffing in activities or inputs, and service intake conditions under external conditions
Reason: This distinguishes actions under management control from external influences.
Imposing the same 4-row, 4-column format on every program
How to revise: Check the commissioning organization’s format and specify outcome levels and definitions
Reason: Logframes have multiple formats.
References and checked sections
- LogframeBetterEvaluation
- Section consulted
- Main text; Advice for using this method
- How it relates to the text
- Logframe formats vary by organization; there is no single universally fixed template.